Project schedule
From materials to grand opening. The highlighted phase is where construction stands today.
Site acquired2024Complete
Washtenaw County acquired the former Cheney Elementary site from Ypsilanti Community Schools after a search of nearly a dozen locations.
Design2025–2026Complete
Neumann/Smith Architecture was selected from 15 firms to design the center. Clark Construction was selected as Construction Manager at Risk.
Material procurementAug – Oct 2026Complete
Building materials are ordered and fabricated so they are ready when site work begins. Bids for underground utilities, foundations, and structural steel have been awarded.
Site grading & utilitiesNov 2026In progress
Earthwork shapes the site and underground utilities are installed. Expect truck traffic on East Clark Road.
FoundationsDec 2026 – Feb 2027Upcoming
Footings and foundations are poured for the building.
Building construction2027Upcoming
Steel goes up, followed by the roof, exterior walls, and interior finishes, including the natatorium.
Grand opening2028Upcoming
The center opens to the community. Date to be announced by Washtenaw County Parks & Recreation.